Laying of the foundation stone of the new building Nova Brunnen stage B1

30.09.2022 | Brunnen

01 Grundsteinlegung

In rainy weather, the laying of the foundation stone for the new quarter ,,Nova Brunnen'' in Brunnen took place on September 28, 2022. It will comprise a total of 101 flats. The site of the Holcim cement factory, which was formerly contaminated, has in the meantime been completely redeveloped and the excavated material disposed of in compliance with standards. The shell will be completed by September 2023 and the clinker facade will be bricked up by the end of October 2023. The handover to the builder is scheduled for November 04, 2024..